Here you will find photos of the entire set construction compilation. Each photo is from the start and end of the day. Newest to oldest! We’re going to be putting it all into a timelapse video on completion. (Day 22 and 23 no pics were taken!)
- Clean up, ready to move in beams and pillars. Last of the building this week!
- Miyuki and Krista clean up the beam and pillar building shenanigans.
- Day 25 begins. Kinda boring today as most of the work was in Chopshop. 😛
- Day 25 ends.
- Day 24 begins. Walls going up.
- Day 24 ends. All wall structures have now been COMPLETE!
- Day 21 Begins. Commence Painting
- Day 21 Ends. Anthony and Emily in Chopshop laying down basecoat
- Day 20 Begins. Setting up for the Beams.
- Day 20 Ends. BEAMS!
- Day 19 Begins. Offload
- Day 19 Ends. Miyuki runs the planks.